1. Home
  2. Building Fire Safety
  3. Guidelines and information
  4. Submitting plans and specifications to FRNSW
Print this page Reduce font size Increase font size

Submitting plans and specifications to FRNSW

Some Fire & Rescue NSW (FRNSW) services require relevant plans and specifications be submitted for review and assessment when the corresponding application form is submitted.

FRNSW accepts digital files that have been submitted electronically as email attachments. The email and attachments must not be more than 20 mb in size. Embedded images should be compressed where possible. All files should be descriptively named to indicate the subject or content. Drawings and plans should be saved as PDF with relevant drawing layers enabled so that each layer can be switched visible/hidden within Adobe Acrobat or Reader.

When required, the following plans and specifications should be provided for assessment:

  • Site plan
  • Floor plans
  • Elevation plans
  • Section views (as appropriate)
  • Schematics
  • Specifications

Note: The applicant is responsible for submitting relevant plans and specifications to FRNSW. If the applicant is simply referring plans and specifications they have received (e.g. a certifying authority referring plans and specifications received with an application for construction certificate), the applicant should verify that relevant plans and specifications they require for determination have been received and are duly referred to FRNSW for assessment. 

 

General requirements for all plans

  • Appropriately referenced drawing title and drawing number including revision numbers and date
  • Appropriately referenced address, building name, lot number, DP number etc.
  • Appropriately scaled with all measurements provided in metric
  • True north indicator provided
  • Appropriately coloured to adequately distinguish various materials to be used and/or distinguish new work from existing

Site plan

  • Show aerial view of whole site including location of new and existing buildings relative to site boundaries
  • Relative location of buildings and infrastructure on adjoining boundary allotments
  • Primary designated building entry point (DBEP)
  • Location and position of building structures (e.g. fire hydrant booster assembly location, bulk water storage tanks)
  • Vehicle access points and car parking areas
  • Internal roadways and driveways providing vehicular access

Floor plans

  • Show aerial view of each floor’s layout including room arrangement within building
  • Use of each room and internal space
  • Location and size of openings including doors and windows
  • Location of vertical shafts, stairwells and corridors
  • Wall structure type and thickness including fire resistance levels
  • Equipment for fire brigade intervention (e.g. fire hydrants, fire brigade panels, isolation valves, WIPs)

Elevation plans

  • Show elevation of all building sides of new and existing buildings
  • Location and size of openings including doors, windows, ducts, vents etc.
  • Location and position of building structures (e.g. fire hydrant booster assembly location, bulk water storage tanks)
  • Exterior cladding type and roofing material

Section views (as appropriate)

  • Show a cut through representation of building construction including where they are on the plan (i.e. A/A, B/B etc.)
  • Height of rooms and openings including doors and windows
  • Construction material details

Schematics

  • Show fire hydrant system plan and/or fire hydrant schematic detailing the system design
  • Show fire sprinkler system plan and/or fire sprinkler schematic detailing the system design
  • Construction material details

Specifications

If not otherwise detailed on the plans and schematics, specifications should be provided detailing:

  • The construction and materials of which the building is to be built
  • Water supply provisions
  • Product specification of hose connections fitted (see FRNSW compatible hose connections)
  • Relevant Australian Standards applicable to the proposed work
  • Details of the performance requirements that an alternative solution is intended to meet, including details of the assessment methods used to establish compliance

Note: Details of an alternative solution are generally provided within a Fire Engineering Report (FER) accompanying an application for construction certificate. The FER is considered a specification of the alternative solution and is attached to the fire safety schedule.